Page D1.28
Answer to the example on page D1.27
(The example on page D1.27, which goes like this, A firm is able to obtain quantity discounts on its orders of materials as follows......)
In the solution where the ordering quantity is 1500, total cost is wrongly calculated.
It is 33,900.83 whereas it should be 39,000+23.33+877.5= 39,900.83