Q. A company is yacht manufacturer. The learning curve of employee of the company is 80%
The unit cost for first unit product
Material cost 10kg x $10 = $100
Direct labor cost 10hrs x $10 = 100
Variable overhead (150% of labor cost) = $150
What is the unit cost for the 10th yacht?
Answer : $208.25 (Sorry, the actual answer should be $219.13)
Anyone want challenge?
dragoon_alex
24-05-08, 12:47 PM
Material cost 10x10 = 100
Labour cost(w1) 47.65
Variable overhead(w2) 71.48
Total cost 219.13
W1
10th bacth cost hr:
10x10^(log0.8/log2)=4.765hr
labour cost= 47.65
W2
Variable overhead = 1.5x47.65=71.48
P.S My answer looks different, is it correct?
lonely_chap911
24-05-08, 09:49 PM
umm i tried but i couldnt find the correct answer :(
Keyperson can u plz explain?
Can someone help me with the formulation of linear programming problem in the question 2B of the june 2008 exam.
Q. A company is yacht manufacturer. The learning curve of employee of the company is 80%
The unit cost for first unit product
Material cost 10kg x $10 = $100
Direct labor cost 10hrs x $10 = 100
Variable overhead (150% of labor cost) = $150
What is the unit cost for the 10th yacht?
Answer : $208.25 (Sorry, the actual answer should be $219.13)
Anyone want challenge?
Material cost 10x10 = 100
Labour cost(w1) 47.65
Variable overhead(w2) 71.48
Total cost 219.13
W1
10th bacth cost hr:
10x10^(log0.8/log2)=4.765hr
labour cost= 47.65
W2
Variable overhead = 1.5x47.65=71.48
P.S My answer looks different, is it correct?
Yes correct answer is 219.125
Kwasi Boadu
14-04-09, 10:22 AM
Can someone kindly post me a copy of the mock exams to kwasi03@yahoo.com.please i do need help because i am short of money.please come to my aid.
Hi,
You can download past exam papers free from the ACCA website.
Give it a go!! Qns and answers..
R Kelly
Powered by vBulletin™ Version 4.0.8 Copyright © 2012 vBulletin Solutions, Inc. All rights reserved.